Tracks & Fields Design
Below is the preliminary conceptual plan (pdf) for the layout of the new track and fields at Homestead High School:
CONSTRUCTION PROGRESS
JULY 2009 The District received approval from the Department of State Architect for Phase One on the Homestead High School tracks and fields project on Thursday, July 31st. Work will begin next week following a similar trajectory as Fremont High. Phase One at Homestead includes all the fields west of where the new football field/bleachers will eventually be constructed. Completion of Phase One will provide the new baseball, softball and multi-use fields to the site by late 2009 or early 2010.
While we are all extremely excited about the positive impact of this project for our students and community, we are also aware that the noise and dust can be a concern. The District and our contractor Robert A. Bothman, Inc. are committed to minimizing the impact on our neighbors and want this to be as positive a process as possible.